Track reconditioning, precast concrete slab installation and post-tensioning at Wollar Creek.

140 m

Track reconditioning

2.4 m

Reconditioning depth

2

Separate work fronts

6 km

Access distance

THE SCOPE

Scope of works

01 / Track reconditioning

140 m of track reconditioning either side of Wollar Creek to a depth of 2.4 m.

02 / Precast concrete

Installation of precast concrete slabs and post-tensioning.

03 / Access & logistics

Two separate work fronts were required, with access over a 6 km distance.

04 / Environment & safety

Working over water required strict environmental controls and working-at-height requirements.